Remove an existing P6 baseline from a P6 schedule.
To remove a P6 baseline from a P6 schedule, complete the following steps:
-
Select the S1 // Projects tab.
-
Do one of the following:
- In the Projects pane, right-click on the P6 project and select
Clear Baseline.
- Select the P6 project in the Projects pane then, in the Get External Data from menu, click
.
The baseline is removed and the black
B (
) on the Primavera P6 file icon in the Projects panel of the workbook no longer displays.